ALBANY — The Dougherty County School Board has approved a recommendation from its buildings and grounds committee to change courses on facility updates at Monroe High School, choosing to build a new gymnasium rather that renovate the existing gym.
The decision will add $8 million to the project’s total cost, boosting the phase II outlay from $27 million to $35 million.
In addition to the new gym, phase II of the project will also include replacing the two-story classroom building. The ninth grade academy will also be replaced, as well as the old lunchroom and kitchen. Renovations will be made to the school’s auditorium.
Board member Darrel Ealum, who is also a member of the buildings and grounds committee, called the work a 40-year investment in the community.
“Communities get a financial opportunity to build a new high school every 40 to 50 years. Our board and the superintendent chose to make a 40-year year investment in a new facility for Monroe High School. When construction on Monroe is complete, 90 percent of Monroe will be new,” Ealum said. “Renovating the old gymnasium and reconstructing the old classroom buildings that had narrow hallways and low ceilings was just not the best long term option.
“With a new gym and state of the art classrooms to enhance the new construction completed several years back, Monroe High School will have an outstanding physical plant we can all appreciate and admire. We took into consideration that rebuilding Monroe High School was a 40-year investment and we chose to build a new facilities with a new gym rather than renovate the old building.”
Ealum pointed out that the school’s old classroom facilities, narrow hallways, poor lighting, and low ceilings will be replaced with state of the art classrooms. The old gymnasium with a seating capacity of 1,000, limited court space, and outdated amenities will be replaced with an 1,800 seated multi-purpose facility which, he said, will rank in the top tier of gyms in southwest Georgia.
“We continually talk about the importance of educating our children and about our commitment to education,” Ealum said. “Well, our board’s investment in Monroe High School will continue to send a strong message beyond Dougherty County that we are committed to raising the educational standards and facilities of our community.”
The project will be funded with a combination of state and SPLOST (Special Purpose Local Option Sales Tax) monies. Work is expected to begin in the summer of 2015 and take nearly 32 months to complete.